    Memphis District’s first IIJA-funded project complete

    The Memphis District recently finished the first Infrastructure Investment and Jobs Act (IIJA) funded construction project on the Mississippi River near Caruthersville, Missouri. The Corps partnered with the Lower Mississippi River Committee (LOMRC) and commercial towing industry to complete the $1.15 million revetment maintenance project at Little Cypress near Mississippi River Mile 863. “Work consisted of placing approximately 43 thousand tons of “Graded Stone C (400 pound maximum stone size)” to repair seven riverbank failures along an approximate 4-mile reach of the existing revetted riverbank,” Project Manager Zach Cook added. “Work started on August 13 and was completed in two weeks."