 |
Making the Numbers Work
Andy Simmerman (right)
and Vee Rogers discuss discrepancies on debris tickets at
the RFO.
LA-RFO Photo by
Spec. Larry Gleeson.
Back
to Features |
An Honest Dollar
Squeezing the "load ticket"
enhances recovery integrity
By Dave Harris, public affairs specialist, Louisiana Recovery Field Office
Related
Stories
Internal
Review: Protecting the Corps reputation as honest broker
The "tower cats" role in
managing the cost of the mission
The human element
and success in flushing out the fudge factor can make or break the
integrity of accurately reimbursing contractors for picking up and
dumping debris removed in South Louisiana, especially as the haul
total approaches enough to fill eight Empire State
Buildings.
The Army Corps of
Engineers role in the National Response Plan benefits taxpayers with
safeguards evolved from years of the industry’s “lessons learned,”
checks and balances, and sound audit principles that ensure accuracy
for both the government and the prime contractors.
The key is
properly completing, tracking, dissecting, scrutinizing and
re-checking the trek of the ever-moving “load ticket,” ensuring
accuracy without running up the cost of the paper trail
authenticating any gaps between claimed and actual loads.
The multiple-copy
load ticket takes a ride from Corps issue at the street or lot
pick-up point, to the truck driver, to the landfill tower, to the
Lake Shore Office for data entry, through multiple QA-QC checks and
eventually to the reconciliation – recon - team at the Louisiana
Recovery Field Office in downtown New Orleans.
When a contracted
debris truck pulls up to a dump site tower – tall enough for a
visual assessment of what’s inside the trailer - the Corps’ quality
assurance inspector from up high sizes up the load. Often the QA
will subtract a specific number of cubic yards based on the size of
the load and perceived voids in the trailer.

Working out the details in the
field
Sizing a load is
not an exact science. It’s a knowledgeable estimate honed by debris
veterans. Specific guidelines, training and enough measures and
eyeballs narrow the room for error to make it a well-informed
entry.
“Calling the load
is like calling balls and strikes in a baseball game,” the Debris QA
Field Guide says. “If the job is done correctly, not everyone will
be happy. The best way to minimize complaints is to call each load
consistently and in a manner fair to the government and to the
contractor. Whenever possible, it is good to have two QA persons
working in the tower and calling each load.”
Corps discussions
with the Army Audit Agency found that both Corps and contractor
workers receive ample training on debris operations and the load
ticket process prior to deployment to the field. Instructions on
responsibilities and step-by-step directions on the completion of
the load tickets are included in the pamphlet each is given.
Any anomalies are
investigated and corrected before final reports for the day’s
activities are generated.
A sloppily
written numeral may be interpreted by one reader as a “9” and by
another as a “4.” Because such mysteries require extra footwork,
trainers emphasize that QAs must practice and insist on legible
entries. Load tickets that are blank or unreadable are returned to
the field for correction. If the load ticket is not corrected, it
is not paid.
QAs account for
blank tickets as if they were blank checks. A stray one in the wrong
hands could cost the government a bundle.
Andy Simmerman, a
civil engineer from Memphis, wrestles down any mismatches that show
up in recon. The contractor submits an invoice for payment along
with supporting data. Recon people enter the contractor’s data into
a “canned-program” spreadsheet specially designed for the LA-RFO
mission that highlights differences between the contractor and
government records.
Andy and others
follow up on discrepancies. “We run it down by tracing it back to
the base document – the load ticket. We make the contractor aware
of the discrepancy and prepare a memorandum for record to
Contracting Division providing a technical payment recommendation,”
Andy said. “Contracting has the final word.”
He added that in
a number of cases, the contractor has billed for less than he was
due.
In addition, the
recon team found between 100 and 150 documented cases for which the
contractor did not have a record and couldn’t bill the Corps -
around 4,500 cubic yards for some $120,000. Subsequently, Corps
records were used to supplement the contractor’s records, which
enabled the contractor to invoice the work.
Dan Mroz from
Kansas City District added that load size isn’t the only challenge,
but the recon process also found QA entries erroneously recording
distances truck travel between the point of origin and the landfill.
“Equitable adjustments had to be made.”
Integrity and
scrutiny serve everyone.

Dan Mroz
Dan said more
than a million load tickets have been generated on this mission.
“The team checks the tickets with the goal of issuing a valid
payment that is fully documented.”
Andy said that
while someone might speculate that “we spend a dollar to chase a
nickel,” the focus is on doing the job right, and without the checks
and balances, “the inspector general would hit [any discrepancies]
out of the park.” More importantly, a system based on integrity
ensures the Corps’ place as an honest broker on the national
response team.
Both agreed that
the lessons learned in this unprecedented mission would pay off in
enhanced procedures on an even wider scale as they are applied to
future disasters, starting with setting up a recon team immediately
after the storm.
A good day is
when a recon specialist can “close out a task order, recommend final
payment and Contracting send a release-of-claims letter for a
particular task order,” Andy said. “Or when you process an invoice
and you and the contractor match on everything.”
And a good day
for Dan? He smiled near the end of his 72-hour week. “Sunday!” On a
more serious note, he added, “And when I don’t have to struggle with
the data base.”
Just like paying
a contractor at home only after he completes work on a new deck,
Jean Todd, Chief of Contracting, explained that the recon process
enables an additional review because a portion of the documented
total is retained prior to payment to insure proper accounting
procedures.
“If it says 100
cubic yards, I want to make sure we got 100 cubic yards,” she said.

The RFO Recon Team |