Memphis District completes $6M in BIL-funded Revetment Repairs
Congratulations to the Memphis District for recently completing a $6M Bipartisan Infrastructure Law (BIL)-funded project at Below Knowlton, Arkansas. “Work to complete revetment stone repairs began on Sep. 27, 2022,” Project Manager Zach Cook said. “Work was then completed ahead of the required completion date on Nov. 8, 2022, despite record low water conditions and stone delivery delays due to tow restrictions.” Contractor Luhr Bros., Inc. from Columbia, Illinois, executed the project work, which consisted of placing approximately 163,000 tons of Graded Stone C (400-pound maximum stone-size) to repair two bank failures. Repairing these banks ultimately restored them to stable slopes.

Download Image: Full Size (0.11 MB)
Photo by: Jessica Haas |  VIRIN: 221125-A-CE999-1001.JPG