  • July

    Relief wells rehabbed, MR&T efficacy ensured

    A Memphis District Project Delivery Team recently completed work to rehabilitate 84 existing relief wells in Crittenden County, Arkansas. “Relief wells significantly reduce the likelihood of a levee breach during high water events,” Project Manager Mark Mazzone said. “Projects like this maintain and rehabilitate relief wells, and directly impact relief well performance and levee protection.”
  • Relief well installation project substantially complete

    A Memphis District Project Delivery Team recently completed work to construct 25 new relief wells in Scott County, Missouri. To execute the project, a contract for $1,630,303.15 was awarded to VuCon, LLC., in August 2018. The contract was administered by the Memphis District’s Caruthersville Area Office, and the job was declared substantially complete June 24, 2022.